| Key data | |
| District | Blasewitz |
| Length of target network 2045 | 1.8 km |
| Heat demand 2045 in the area | 7.5 GWh/a |
| Heat load 2045 in the area | 4.7 MW |
| Potential energy sources for heat generation |
|


| Existing buildings (values based on the heat register of the state capital Dresden) | |||
|---|---|---|---|
| Energy reference area | 91.880 m² | Number of buildings | 99 |
| of which residential | 54.535 m² | Number of residential units | 532 |
| of which commercial/industrial/public | 37.345 m² | Proportion of listed buildings | 37% |
Current structure in the neighbourhood

Anteil Energieträger am Endenergiebedarf

Anteil Energieträger am Endenergiebedarf

Verteilung Baualtersklassen (Anteile an EBF)

Verteilung Baualtersklassen (Anteile an EBF)

Verteilung Heizungsalter (Anteile an EBF)

Verteilung Heizungsalter (Anteile an EBF)

Eigentumsverhältnisse (Anteile an EBF)

Eigentumsverhältnisse (Anteile an EBF)
GHD = trade, commerce, services
EBF = Energy reference area
WP = heat pump
Detailed information
| Development of heat demand and emissions | Stock | 2045¹ |
|---|---|---|
| Final energy demand incl. environmental heat (GWh/a) | 9,9 | 7,6 |
| spec. final energy requirement (kWh/m²a) | 108 | 83 |
| Greenhouse gas emissions (tCO2eq/a) | 2.427 | 103 |
| Heating network | |||
|---|---|---|---|
| Total investment framework | eUR 6.49 million | BEW subsidy (40%) | eUR 2.60 million |
| of which distribution grid | eUR 3.42 million | of which distribution grid | eUR 1.37 million |
| of which heat generation³ | eUR 3.07 million | of which heat generation | eUR 1.23 million |
¹) Assumption: Local heating connection rate 75% and 25% decentralised air-to-water heat pumps
³) Assumption: air-to-water heat pump 1.9 MWth, peak load boiler 2.3 MWth, heat storage tank 5 MWh





Wärmenetzgebiet und grobe Trassenlage

Wärmenetzgebiet und grobe Trassenlage

Eigentumsverhältnisse unbebaute Flächen ²

Eigentumsverhältnisse unbebaute Flächen ²
²) Developed area <5%
| Period | ||
|---|---|---|
| Acquisition of network operator and early commitment of heating customers | Firstly, clarify again whether district heating can be connected after all (depending on the results of the hydrogen grid test by 2028), if local heating network then anyway:
| 2028 |
| Planning and securing land |
| 2029-2034 |
| Realisation | Construction of energy centre, development of heat sources (geothermal probe field / air-water heat pump), pipe laying, construction of house connection stations | 2035 - 2037 |